Kitchen Remodel Payment Schedule: Milestones, State Deposit Caps and a Worked Example
Most kitchen remodel contracts use four to six draws tied to milestones: deposit at signing, demo complete, rough in passed, cabinets set, and punch list done. At least three states cap your deposit by law, some as low as $1,000 [1]. Build your schedule around those caps and you stay compliant without choking cash flow.
By Joe Petocz, EstimateElite. Updated .
Which states cap your deposit?
Most states have no statutory cap on how much you can collect upfront on a home improvement job. But several of the biggest remodeling markets do, and the limits vary widely.
California is the strictest. The down payment cannot be more than $1,000 or 10 percent of the contract price, whichever is less 1. On a 150 square foot modern kitchen priced at $53,361 in our data, ten percent would be $5,336, so the $1,000 ceiling is what actually controls. California also says that after the down payment, progress payments to the contractor cannot exceed the value of the work performed 1. That means every progress draw must match what you have actually completed at that stage.
Maryland caps the deposit at one third of the contract price 2. On that same kitchen, the maximum deposit is $17,787. Maryland also prohibits any payment until the contract is signed 2. Beyond the initial deposit, the Home Improvement Law does not control the payment schedule 2, so you structure later draws however you and the homeowner agree.
Massachusetts has the same one third cap. The deposit cannot exceed one third of the total contract price 3. The contract must include the payment schedule, with the dates and the amount of each payment stated in dollars, including any finance charges 3. And final payment cannot be demanded until the contract is completed to the satisfaction of all parties 3.
New York has no dollar cap, but every progress payment must bear a reasonable relationship to the amount of work to be performed, materials to be purchased, or expenses 5. Pre completion payments must go into an escrow account at a New York bank or be backed by a surety bond 45. Violations carry fines of $250 to $2,500 for payment protection violations 4.
Texas has no deposit cap either. But construction payments on residential improvements are legally trust funds 6. A contractor who misapplies those trust funds with intent to defraud commits a felony of the third degree 6. That means your draw money must go toward the project it came from, not your truck payment or another job.
| State | Max deposit | Additional payment rule |
|---|---|---|
| California | $1,000 or 10%, whichever is less [1] | Each progress draw cannot exceed value of work completed [1] |
| Maryland | 1/3 of contract price [2] | No payment before contract is signed [2] |
| Massachusetts | 1/3 of contract price [3] | Exception for special order materials at actual cost [3] |
| New York | No dollar cap | Pre completion payments held in escrow or bonded [5] |
| Texas | No dollar cap | Payments are construction trust funds on residential jobs [6] |
Five milestone draws for a kitchen remodel
Tie every draw to something the homeowner can see or an inspector has signed off on. Never tie a payment to a calendar date. If drywall gets delayed two weeks because of a material backorder, a date based schedule forces you to have an awkward conversation about collecting money for work that has not happened. A milestone based schedule avoids that entirely.
Here are five milestones that work for most kitchen remodels.
- Deposit at signing. Collected after the cancellation period passes. Covers initial mobilization, permits and material ordering.
- Demo complete and rough in passed. Old kitchen is stripped. Plumbing, electrical and gas rough ins are installed and have passed inspection.
- Drywall hung and cabinets set. Walls are closed, taped and finished. Cabinets are mounted, level and plumb.
- Countertops installed and finish work complete. Counters are templated, fabricated and set. Backsplash, paint, flooring and trim are done.
- Punch list complete. The homeowner has walked the project. Every item on the list is addressed. Final payment is released.
Worked example: your deposit on a $53,000 kitchen
A 150 square foot modern kitchen runs $53,361 in our pricing data. Here is what you can legally collect on day one in each of these states, and what that means for your first week of cash flow.
In California, you collect $1,000 at signing and carry $52,361 until the first progress draw 1. That means you need your first milestone to come fast. Structure it so the first progress payment arrives as soon as demo is complete, usually within the first week. You can point to visible work and bill for the value of what was done.
In Maryland or Massachusetts, you can collect up to $17,787 at signing 23. That is enough to cover material ordering, mobilization and the full cost of demolition before you bill again. With a larger deposit you can run fewer milestone draws after it. Three or four milestones after the deposit is common in these states.
In states with no cap, your deposit is whatever you and the homeowner agree to. Keep it large enough to cover material ordering and mobilization but small enough that the homeowner feels protected. Then split the rest across your milestones.
| State | Max deposit on this job | Balance after deposit |
|---|---|---|
| California [1] | $1,000 | $52,361 |
| Maryland [2] | $17,787 | $35,574 |
| Massachusetts [3] | $17,787 | $35,574 |
| New York [5] | Negotiable (held in escrow) | Varies |
| Texas [6] | Negotiable (trust fund rules) | Varies |
| No cap state | Negotiable | Varies |
EstimateElite shows you every homeowner's budget before you pick up the phone. See how the setup works
Custom cabinets and the special order exception
Custom or semi custom cabinets are the largest single line item on most kitchen remodels. On the $53,361 kitchen in our data, cabinetry alone accounts for $14,350. If you need to place a cabinet order weeks before demo day, the deposit cap can create a real cash flow problem.
Massachusetts addresses this directly. The deposit limit is one third of the total contract price or the actual cost of any material or equipment of a special order or custom made nature, whichever is greater 3. If your cabinet order exceeds one third of a smaller contract, you can collect the full material cost upfront in Massachusetts as long as the material must be ordered in advance to keep the project on schedule.
California has no such exception. The $1,000 cap applies regardless of what you need to order 1. Your options in California are to carry the cost yourself, ask the homeowner to order directly from the supplier and pay the supplier, or negotiate terms with your cabinet vendor so you do not pay the full amount until installation week.
What your contract must say about the payment schedule
Every state that regulates home improvement contracts requires the payment schedule to be in writing. California requires a detailed, written payment schedule in the contract 1. Massachusetts requires the payment schedule, with the dates and the amount of each payment stated in dollars 3. New York requires a schedule of progress payments showing the amount of each payment in dollars and cents and specifically identifying the stage of completion 5.
Even in states with no specific statute, a written payment schedule protects you. Without one, you have no enforceable right to collect at a milestone. The homeowner can dispute any draw and you have nothing in writing to point to.
Your contract payment section should include at minimum:
- Each milestone described in plain language the homeowner can verify
- The dollar amount due at each milestone
- A statement that payment is due upon completion of the milestone, not on a calendar date
- The total contract price
- How change orders affect the schedule, with each change order carrying its own payment terms
- In New York: the name and address of the escrow bank or the surety bond details 5
Decision rule: how many draws do you need?
The number of draws depends on how much you collect upfront. In California, you are starting with $1,000. You need more milestones to stay cash positive through the job. Five or six draws is the norm. In Maryland or Massachusetts, the one third deposit gives you a bigger cushion. Four milestones after the deposit is usually enough.
In states with no cap, match the number of draws to the complexity and length of the project. A straightforward cabinet and countertop swap might need three draws. A full gut renovation with structural work, new plumbing runs and a relocated island might need six or seven. Each draw should represent a meaningful chunk of completed work that the homeowner can verify before writing a check.
Whatever your state allows, hold back a final draw that is only released after the punch list walkthrough. This protects the homeowner and gives you a clear finish line. When homeowners know the last payment is tied to their satisfaction, they are more likely to pay the earlier draws without pushback.
Know the budget before you write the payment schedule
EstimateElite screens every inquiry you already get so you know the project scope and what the homeowner is ready to spend before you pick up the phone.
Common questions.
In Maryland, no. The law prohibits any payment until the contract is signed [2]. In most other states, the deposit is collected at signing or after. As a practical matter, never collect money before the contract is signed. If the homeowner later claims there was no agreement, you have no written proof of what the money was for.
Sources
- Learn About Home Improvement Contracts, California Contractors State License Board
- Home Improvement Contracts, Maryland Department of Labor
- Home Improvement Contract Requirements, Commonwealth of Massachusetts
- Home Improvement Fact Sheet, New York State Attorney General
- General Business Law Section 771, New York State Legislature
- Property Code Chapter 162: Construction Trust Funds, Texas Legislature
Where EstimateElite fits
- Pipeline and inbox
Drag a lead across your stages, open it to see the price they saw and the finish they picked, and reply from the same screen. Your close rate, pipeline value and won value sit at the top.
- Schedule
Set your hours once. Homeowners pick a time that is really open, because the schedule syncs with your Google Calendar and blocks anything you already have.
- EstimateElite vs Buildertrend
Buildertrend runs the build. EstimateElite runs the week before it.
- Estimating software for remodelers, compared
What each kind of tool does, the products remodelers compare, and where each one stops.